New-Build (VEFA) Delivery: Pre-Handover or Handover?

In short. A pre-handover visit is not the handover. The first is a preparatory visit with no legal effect of its own; the second, with the keys and a signed report, starts the clock and fixes your snagging list. Sign nothing on the day without walking through the property with a technical eye, and report visible defects without delay.

Your situation in brief

You bought off-plan (VEFA, the French sale of a property still to be built) and the developer announces that the works are finished. You are offered a “pre-handover” visit, then a “handover”, with a report to sign and the keys at the end. Between the two, many buyers hesitate: what can be done at each stage, what commits you, and when is it better to refuse the keys?

Pre-handover and handover: the difference

  • The pre-handover visit (pre-acceptance) is a visit arranged, usually a few weeks before the keys are handed over, to spot defects and give the developer time to fix them. It is not required by law and does not amount to acceptance: use it to note everything.
  • The handover is the delivery of the property to the buyer, with a report listing the snags. It marks the buyer’s acceptance of the works and the start of the statutory warranties.

The first five steps

  1. Prepare the visit: plans, specification notice, reservation contract and deed of sale in hand, to compare what is delivered with what was promised.
  2. Inspect with a technical eye: flatness, plumb, cracks, waterproofing, ventilation, joinery, electrics, floor areas, fittings.
  3. List the snags on the report, precisely (room, nature, location), and illustrate them with dated photographs.
  4. Refuse vague wording such as “subject to finishing touches”: insist on a detailed list and a date by which each item is cleared.
  5. If the defects are significant, you may refuse to take delivery and ask for a new visit, rather than signing in the hope of a correction.

What to avoid

  • Signing the report “without reservation” under pressure from the calendar or an oral promise.
  • Forgetting defects found after the visit: they must be notified to the developer in writing within one month of taking possession.
  • Paying the balance of the price without allowing for a dispute over conformity.

What the law says, in plain terms

The seller cannot be released from liability for visible construction defects or non-conformities, either before acceptance of the works or before one month has passed after the buyer takes possession (article 1642-1 of the French Civil Code). Visible defects must therefore be reported within that period at the latest.

After handover, the one-year warranty of perfect completion covers the defects reported, the two-year warranty covers certain fittings and equipment, and the ten-year warranty covers serious damage (articles 1792 and following of the Civil Code).

Where the buyer disputes that the property conforms to the contract, the balance of the price (5%) may be placed in escrow rather than paid to the developer, under the conditions set by law and by your contract (article R. 261-14 of the Construction and Housing Code).

How we help

We go with you to the pre-handover visit and the handover: we check the property against the plans and the specification, with measurements (level, plumb, humidity, thermal camera where relevant), and we draw up the snagging list with you.

After handover, we follow up the clearing of the snags and, if the developer does not correct them, we write a report that supports the formal notice. We do not sell building work: our opinion is independent of the developer and of the contractors.

Frequently asked questions

Is a pre-handover visit compulsory?

No. It is a trade custom, and a very useful one. If the developer does not offer it, you can ask for it: it reduces the risk of discovering the defects on the day the keys are handed over.

Can I refuse the keys if the property does not conform?

If the defects are significant, you may refuse to take delivery until the property is in order. The decision calls for care: talk to an expert or a lawyer before communicating it in writing.

What if the developer does not clear the snags?

Send a formal notice by registered letter listing the outstanding snags, and have a technical report prepared. If the deadlock continues, that report supports a request to place the balance in escrow or legal action.

Further reading

Other situations

Does this sound like your situation?

Tell us about your case: free quote within 24 hours, independent expert, no building company behind us. We speak English.

Contact us +33 4 22 46 06 04

First video consultation: terms and conditions

General information, up to date as of 14 November 2026. It does not replace legal advice or a review of your documents.