Building survey – VEFA (off-plan purchase)
You have just received the keys to your new apartment in Nice. The VEFA plan (vente en l’état futur d’achèvement, an off-plan purchase) promised a bedroom of 12 m². You measure: 10.8 m². That is 1.2 m² missing, a 10% discrepancy. The developer tells you: “It’s within tolerance.” Is that true? Not so simple.
What You See, and What It Really Hides

On the plan, the bedroom is a perfect rectangle of 3.00 m × 4.00 m. In reality, a fire wall running through the room reduces the width to 2.70 m. To the naked eye, you don’t see the difference. But with a laser distance meter, the gap is obvious. What we often see on deliveries in Nice: developers play on partition thicknesses, technical ducts, or façade offsets not shown on the plan. The VEFA plan is a contractual document, but it is not always consistent with execution.
In a case in Nice last year, we measured a living room supposed to be 25 m²: it was 23.1 m². The developer invoked a 5% tolerance. Standard NF EN ISO 5455 does not provide one: it concerns scales on technical drawings, not delivered areas. The French Civil Code does set a one-twentieth (5%) threshold for differences between the area stated in a sale contract and the area delivered (art. 1619), but how it applies to an off-plan (VEFA) contract depends on the contract and is a question for a lawyer.
The Calculations That Change Everything
Let’s take a typical case in Nice: a bedroom advertised as 12 m². Actual measured area: 10.8 m². Difference = 1.2 m², i.e., 10%. Standard NF EN ISO 5455 concerns drawing scales, not delivered areas. The Civil Code sets a one-twentieth (5%) threshold for differences between stated and delivered area (art. 1619); here the difference is 10%, twice that figure. Whether the buyer can claim a price reduction or rectification is a legal question for a lawyer.
In concrete terms, your bedroom of 10.8 m² instead of 12 m² is a 10% deviation. That’s twice the tolerance. What this means: you can ask for a proportional price reduction or rectification. In Nice, the market is tight: one m² is worth on average €6,000. The developer knows this and often prefers to negotiate.
What Happens If You Do Nothing
Six months after delivery, you want to resell. The notary measures: 10.8 m². The price drops by €7,200. Worse: if the deviation exceeds 5%, the next buyer can sue you for hidden defects. You lose twice.
At two years, micro-cracks appear around the fire-rated wall not shown on the plan. The poorly positioned technical duct reduces sound insulation. Neighbours complain. Without a remedy, you bear the whole cost.
Remedies and Guarantees: What You Can Ask For
French law requires the seller to deliver a property that conforms to the contract (Civil Code, arts 1604 and 1642-1). In an off-plan sale, the seller remains liable for apparent defects and non-conformities until one month after the buyer takes possession (art. 1642-1), and the action must then be brought within one year of that date (art. 1648, para. 2). A lawyer can advise on formal notice and court action. An expert report with laser distance meter measurements documents the deviations.
Further reading:
Frequently asked questions
What is a VEFA plan in Nice?
A VEFA plan in Nice refers to the purchase agreement for a property before completion (vente en l'état futur d'achèvement). It outlines the delivery timeline, specifications, and legal protections for buyers, ensuring the developer completes the property as promised.
How do you detect hidden non-conformities at VEFA delivery?
At delivery, hire an independent expert to conduct a thorough inspection, compare the finished property against the VEFA contract's detailed plans and specifications, and check for issues like material substitutions, size discrepancies, or missing features. Document everything and report any non-conformities to the developer within the legal timeframe.
What are common non-conformities in VEFA properties?
Common issues include changes in materials or finishes, incorrect room dimensions, missing amenities like balconies or parking spaces, faulty installations (plumbing, electrical), and delays in completion. These can often be hidden, so professional verification is crucial before you sign the handover report.
See also: Reading a VEFA Plan in Nice: Spotting Non-Conformities at Delivery · VEFA Delivery Delay: What Recourse Does the Buyer Have? · VEFA Delivery Delayed in Cannes-la-Bocca: Your Compensation
Survey carried out by Frédéric Faucouneau, independent building expert, Antibes, Alpes-Maritimes (06), Var (83), Bouches-du-Rhône (13). Last updated: 26 November 2026. Find out more
Last updated 26 November 2026 - Cassini Expertise, independent building expert, departments 06, 83 and 13.