In short. The balance is normally due on acceptance, not before. If the contractor demands it while the work has not been accepted or defects remain, do not pay before the condition of the work has been recorded: full payment together with taking possession can be read as tacit acceptance, and you would lose your main lever.
Your situation in brief
The work is finished – or nearly – and you have paid instalments, sometimes almost everything, but no acceptance report has been signed. The contractor demands the balance, with reminders, sometimes penalties or a threat of proceedings. On your side, you see missing finishes and defects, or you simply have doubts.
The central point is acceptance (réception): it fixes the moment when the balance becomes payable and when the statutory warranties start.
The first five steps
- Reread the contract and the payment schedule: at what stage is the balance due? Is a retention provided for?
- Do not sign an acceptance report « to get it over with » without walking through the work room by room with a technical eye.
- Have the condition of the work recorded, preferably in the presence of both sides (the contractor invited): list of defects, dated photographs, measurements.
- Reply in writing, by registered letter with acknowledgement of receipt: you dispute that the balance is due, you list the points in dispute, and you propose a date for a joint acceptance.
- If matters drag on, propose an amicable expert assessment – a single expert, or one each – before any costly legal step.
What to avoid
- Paying the whole balance and taking possession « without saying anything »: it may be analysed as tacit acceptance.
- Refusing to pay without writing or justifying anything: the contractor can sue you for payment.
- Having the defects repaired by another contractor before they are recorded: you would destroy the evidence.
- Relying on text messages or a verbal agreement.
What the law says, in plain terms
Acceptance is the act by which you accept the work, with or without reservations (article 1792-6 of the French Civil Code). It can be express (a signed report), tacit (conduct that shows unequivocally an intention to accept) or judicial (declared by a judge). It is the starting point of the one-year warranty of perfect completion, the two-year warranty and the ten-year warranty.
In private works contracts covered by the law of 16 July 1971, a retention cannot exceed 5% of the price; it is normally released one year after acceptance if the snags have been cleared.
You may set against the contractor the defence of non-performance (article 1219 of the Civil Code) where it has not properly performed its part and the breach is sufficiently serious: you still have to demonstrate it, and remain proportionate.
How we help
We act as an independent expert: we sell neither building work nor materials. We visit the work, record the defects with measurements and dated photographs, rank them by seriousness and cost the repairs needed. That record lets you answer the contractor with precise facts and withhold a justified amount rather than an arbitrary sum.
We can attend the acceptance meeting, or conduct an amicable expert assessment with the contractor. A first video consultation is often enough to decide how to proceed.
Frequently asked questions
Can I withhold the whole balance until the defects are repaired?
Not without care. The law allows you to refuse payment in proportion to a sufficiently serious breach, but an excessive withholding exposes you to a claim for payment. It is better to have the repairs costed by an expert and withhold a justified amount, in writing.
What happens if I take possession without signing a report?
The contractor may argue that there was tacit acceptance, especially if you paid the whole price. Judges decide case by case. If you take possession, state immediately in writing that you do so without accepting the work, and list your reservations.
The contractor threatens proceedings: what should I do?
Reply in writing, stay factual and propose an acceptance meeting or a joint assessment on a precise date. A proposal for an amicable assessment shows your good faith and prepares the file if the dispute goes to court.
Further reading
- Handover inspection: avoiding implicit acceptance of defects
- Defects after handover: your options
- Amicable or judicial building expertise: what is the difference?
- Construction defects and ten-year liability
Other situations
- Your Insurer Limits Its Cover: What You Can Do
Insurer refusing, reducing or capping your claim? Dommages-ouvrage, natural disaster and home insurance: your options and how an expert helps. - Amicable Expert Assessment: Avoiding a Costly Court Expert
A court-appointed expert costs money and takes months. An agreed amicable expert assessment: when it is enough, how to set it up and its limits. - Cracked or Falling Facade: Who Is Liable?
Widening cracks, render or stones falling: builder, owner, managing agent, neighbour? Safety first, then evidence and your options, step by step. - New-Build (VEFA) Delivery: Pre-Handover or Handover?
Buying off-plan (VEFA): what is the pre-handover visit for, when do you sign the handover, how to record snags and what to do about the balance.
Does this sound like your situation?
Tell us about your case: free quote within 24 hours, independent expert, no building company behind us. English spoken.
First video consultation: terms and conditions
General information, up to date as of 14 November 2026. It does not replace legal advice or a review of your documents.
Last updated 13 November 2026 - Cassini Expertise, independent building expert, departments 06, 83 and 13.